Image
File Photo

Petrolia spends $300K to get three streets covering half kilometre ready to fix

June 27, 2025

Heather Wright/The Independent

The Town of Petrolia will spend over $300,000 for engineering services to rebuild about a half a kilometer of streets.

Mike Thompson, director of operations, says the town needs to plan to rebuild three smaller streets, King, Hickory and School, in the oldest part of the community.

“For several years King Street has been on staff’s radar as it has deterioratred signifcantly over the last decade,” he writes in a report to council. “In 2025 to date we have experienced two significant water main breaks.” He says the town’s long term capital plan calls for a full reconstruction.

One of the more significant problems on King is the hydro poles which are built into the street.

Thompson says Bluewater Power says they can be moved off the street. He tells The Independent the power company decided to continue using poles in the area instead of burying the hydro service.

King Street is about 350 meters long.

Hickory and School Streets also need new water, storm, and sanitary sewers, Thompson says.

“Hickory and School Streets are the remaining streets in town that do not have curb and gutter structure, with the road surface being beyond a shave and pave repair,” he writes. Some of the streets are mainly gravel.

Thompson says the two streets, both about 100 meters long would be rebuilt and sidewalks added.

The three streets all need civil engineering studies for preliminary and detailed designs which are needed to obtain grants for the work.

A cost for the projects has not been estimated yet, however Thompson writes it will cost about $201,885 for the engineering services related to King Street excluding any environmental inspections or testing of the materials during construction and $162,962 for engineering Hickory and School Streets.

Once the work is complete, Thompson said the town would be able to apply for grants. It’s possible some of the work could move ahead in 2026, particularly on King Street which is seen as a priority.

Share This

Image
Front Page

Lambton-Kent public school board to hold fewer public meetings

October 2, 2026

Blake Ellis/The Independent The Lambton Kent District School Board will have 15 meetings annually beginning in November. A revised plan was presented to trustees at its Sept 22 meeting after trustees voted down a plan in a 4-4 vote at its Sept. 8 meeting to reduce its schedule from 18 meetings to nine meetings. Trustee David Shortt said the new

Read More

Image
Front Page

Electric Zamboni sweeping East Lambton ice

October 2, 2026

The Independent Warwick Township has a new, much quieter Zamboni cleaning up at the East Lambton Community Complex. The township took delivery of its first ever electric Zamboni recently. The $150,000 machine was ordered in 2025 and the township waited two years for the order to be filled. Parks and Recreation Manager Ryan Chamney says the electric Zamboni is a

Read More

Image
Front Page

Mega road project gone awry, now a mega election issue

October 2, 2026

Cathy Dobson/The Independent As Point Edward residents consider who to vote for, the biggest road redevelopment contract in the village’s history is raising a lot of questions. Reconstruction of five large blocks of St. Clair Street that started in early spring 2024, was expected to last about a year and cost approximately $5.4 million. But more than two years later,

Read More

Image
Front Page

Langstaff honoured provincially for 4H volunteering

October 2, 2026

The Independent Lambton County 4H leader Tami Langstaff is being honoured for her volunteerism. She was one of six people across the province receiving the 4-H Ontario Outstanding New Volunteer Award. Langstaff has been involved in 4H in Lambton since 2022, helping the clubs with everything from line dancing to crocheting. She also serves on the association’s board and helps

Read More