Image

Demolition of Lambton Generating Station to take two more years

February 10, 2021

Delsan-A.I.M. workers at work now

Heather Wright/The Independent

Demolition work on the Lambton Generation Station is expected to restart in the next few weeks but will take two years to finish.

The former coal fired plant was partly dismantled by JNX Contracting over the course of the last two years. But in March 2020, the pandemic hit and the decommissioning stopped.

Then, in May, JNX Contracting declared bankruptcy.

Ralph Curitti, the project manager for Ontario Power Generation which owns the plant on the St. Clair River near Courtright, says OPG had to wait for the bankruptcy courts approval. “In that process, there are certain protections, so that they were given time to sort of restructure the business. We didn’t take any action against them in that regard,” Curitti says, “at least until we received permission from the court to terminate that vendor and get another vendor.”

OPG has just signed a contract with Delsan-A.I.M. to take down the rest of the plant. Delsan-A.I.M. completed the demolition of OPG’s Nanticoke coal fired plant in 2017.

“They’re just currently there on site, just sort of mobilizing, preparing their construction island and getting ready to start the work,” says Curitti. “I would say in the next couple of weeks, you’ll see some activity starting up.

“Our objective is to have the project completed by the end of 2022.”

Curitti says the company will first remove all the asbestos on the site. “And then you’ll see, essentially, a lot of the smaller buildings and around the front of the property closer to St. Clair Parkway start to get cleared up, and they’ll be demolished and backfilled.

“And then at that point, the boilers themselves would come down, we have that currently scheduled to come down end of November, beginning of December of this year. And then, once those are down, it’s a matter of just clearing up all that scrap and preparing the chimneys for their demolition.”

That’s the part that concerns St. Clair Township Mayor Steve Arnold. He says residents in the Courtright area have been patient through the two or three years OPG has been working on the site and they’ll be glad to see the work complete.

But he’s concerned about the way the company plans to bring down the giant chimneys at the front of the building.

OPG’s original plans call for the cement cylinders to be imploded. Arnold says his council and the community don’t like that idea at all.

“We’ve made it very clear, we don’t want them imploded,” says Arnold. “We want them removed and we’re getting a lot of pushback from them on that.”

Arnold says council has asked the chimneys be dismantled with a large crane, just like they were erected. He says dropping the chimneys with implosions would create a lot of debris which is potentially toxic.

“The switchyard is right there, we got Courtright, right there, we have all those people up and down the river, on both sides.,” he says.

Implosion, Arnold says, is “the easy way out, it’s just to have a big explosion dropped them. Do you really care about the neighbors? You really question whether anybody’s too concerned about the people live around there because that old cement – a lot of it was built with asbestos and such for fibers within it.”

But the plans have not changed with the new contractor stepping in.

“Our plan is to still use an implosion methodology. The plan is to bring down the chimneys around August of 2022 timeframe,” says Curitti.

“I don’t believe that the stacks would reach the roadway ..we’re quite confident that, that that would go smoothly. The vendor that we have, they did just recently complete the demolition of the Nanticoke generating station, which had two very large chimneys as well, and those went down without a hitch,” he adds.

“We’ll obviously be doing all the sort of environmental specs, making sure there’s no environmentally sensitive materials in the chimneys.

“We have no reason to believe at this time that they have anything other than just regular concrete in them.”

Arnold would like to see OPG answer to the public for its plan. “They need to go out to the public and not through council or through the mayor’s chair. It needs to go out into public meetings, again, by the new contractor, to assure these people that things are going to be done in an environmentally safe manner.”

The asbestos removal is expected to start in a couple of weeks with about 40 people onsite doing the work.

Curitti says the demolition company will take the scrap steel for payment – estimated to be worth about $24 million. OPG had already paid JNX about $3 million for its work.

The company which will complete the demolition of Lambton Generating Station also worked at the Nanticoke Generating Station. Here’s video of the stacks dropping there in 2018.

Share This

Image
Front Page

Lambton County Plowing match draws more competitors than usual as 2027 IPM in Petrolia nears

September 14, 2026

Blake Ellis/The Independent Enniskillen Mayor Kevin Marriott may not have a municipal election contest this year, but he did face some of his political colleagues at the Lambton County Plowing Match. And Marriott, who is also Lambton’s Warden, handily handled the competition. Marriott won the annual plowing contest between politicians over St. Clair Township Mayor Jeff Agar, Plympton-Wyoming Mayor, Gary

Read More

Image
Front Page

Oil Springs okays asset retirement study

September 14, 2026

Blake Ellis/The Independent It turns out the cost to complete asset retirement obligation estimates on its five municipally-owned buildings is much less than the Oil Springs council expected. The study will determine the cost of abatement of designated substances, such as asbestos, lead, silica and mercury, during decommissioning and demolition at the end of each building’s life. This will better

Read More

Image
Front Page

NPHL shrinks as Stratford and Halton Hills bow out this season

September 14, 2026

Barry Wright/The Independent The Alvinston Killer Bees will not be taking trips to Stratford or Halton Hills during the upcoming Northern Premier Hockey League season. Following the completion of a league review, the NPHL says the operations of the Irish and Coyotes franchises have been suspended for the coming season and despite the Irish posting that they fully intend on

Read More

Image
Front Page

Lambton to study truck traffic on Oil Heritage in 2027 preparing for York 1 transports to Dresden

September 11, 2026

Heather Wright/The Independent It will be 2027 before Lambton County takes a close look at truck traffic patterns on Oil Heritage Line. Plympton-Wyoming council is asking for an origin-destination study of Oil Heritage Road – which includes Wyoming’s main street – as concerns mount about increased traffic due to the rehabilitation and expansion of a dump near Dresden. The town

Read More