Image

It’s coming down to the wire as construction crews push to complete the first phase of Petrolia’s Big Dig.

In July, Birnam Construction began rebuilding Petrolia Line. It’s a two-year, $4.5 million project which will see water and sewer lines beneath the main street replaced and new roads, curbs and sidewalks completed on the surface.

From the beginning, town officials were adamant the work would be complete by Nov. 15. Mike Thompson, Petrolia’s director of operations, oversees the project. He says the construction crews are expecting to be done very close to that date.

Thompson says there were a number of problems which caused delays which will push the completion date back to Nov. 22. One of the big problems was water main breaks.

“They’re beyond their control,” says Thompson. “It translates into more money which comes out of a contingency fund and then, more time. They get a change order (which town council approves) when it comes to unforeseen things that delay the project.”

At the last town council meeting Oct. 26, there were three change orders for a water main break, removing an abandoned gas line and moving a manhole cover. The contract sets aside $150,000 for unforeseen problems – by Oct. 26, $102,372 had been used.

Thompson says all those problems have made the timeline tight for Birnam. “They asked for an extension, but we said no,” says Thompson. “All they wanted was an (extra) week. But we said no. They’ve been saying it is going to be done…so we said no. It’s up to them.”

Saturday, construction crews could be seen working on the site, presumably to try to finish the job by Nov. 22. Every day after that date, Birnam faces a monetary penalty.

But Thompson is hopeful the crews will be able to finish the job on time finishing the underground services this week and paving and laying sidewalk next week. “Starbright (Christmas productions) start on the 24th so we’d like to have the road open by then,” he says. “It is important for the business for the road to be open and for the people of the town for the road to be open.”

Share This

Image
Front Page

Sarnia all-candidates debate a revealing evening

October 21, 2026

Cathy Dobson/The Independent With less than a week until election day, 28 candidates vying for eight council seats, spent four hours Tuesday trying to stand out as the right choice for Sarnia voters. They gathered at The Imperial Theatre in front of an audience of 200, with another 500 streaming the marathon event online. Compared to Monday night’s mayoral debate,

Read More

Image
Front Page

St. Clair will be reimbursed for help at Chatham ethanol plant fire

October 21, 2026

Heather Wright/The Independent St. Clair Township Councillor Brad Langstaff wants to know what it cost for the fire department to help fight an ethanol plant fire in Chatham. Sept. 16, 15 firefighters, the township’s two tower trucks and its drone headed to Chatham to help battle a massive fire at Greenfield Global. St. Clair was called on because it has

Read More

Image
Front Page

Enniskillen rejects request for ATVs on township roads

October 21, 2026

Blake Ellis/The Independent ATVs won’t be allowed on Enniskillen roads. A request by Enniskillen Resident Mark Braet failed to sway Enniskillen Township Council to allow all terrain vehicles on township roads. Braet made a presentation to council on Oct. 8 along with representatives from the Tri-Shore ATV Club. Braet wanted to be allowed to drive ATVs on roads in the

Read More

Image
Front Page

LAMBTON VOTES: Petrolia Candidate Surveys

October 21, 2026

The Independent sent a questionnaire to each candidate for Petrolia Council. Below are the unedited responses from the candidates: Work Experience: Policy Advisor, Sarnia-Lambton Chamber of Commerce; former Constituency Assistant to MPPs Bob Bailey and Billy Pang; former parliamentary intern with MPs Marilyn Gladu and Jake Stewart; former Town of Petrolia Parks & Recreation Summer Labourer; former Dietary Aide at

Read More