Image

It’s coming down to the wire as construction crews push to complete the first phase of Petrolia’s Big Dig.

In July, Birnam Construction began rebuilding Petrolia Line. It’s a two-year, $4.5 million project which will see water and sewer lines beneath the main street replaced and new roads, curbs and sidewalks completed on the surface.

From the beginning, town officials were adamant the work would be complete by Nov. 15. Mike Thompson, Petrolia’s director of operations, oversees the project. He says the construction crews are expecting to be done very close to that date.

Thompson says there were a number of problems which caused delays which will push the completion date back to Nov. 22. One of the big problems was water main breaks.

“They’re beyond their control,” says Thompson. “It translates into more money which comes out of a contingency fund and then, more time. They get a change order (which town council approves) when it comes to unforeseen things that delay the project.”

At the last town council meeting Oct. 26, there were three change orders for a water main break, removing an abandoned gas line and moving a manhole cover. The contract sets aside $150,000 for unforeseen problems – by Oct. 26, $102,372 had been used.

Thompson says all those problems have made the timeline tight for Birnam. “They asked for an extension, but we said no,” says Thompson. “All they wanted was an (extra) week. But we said no. They’ve been saying it is going to be done…so we said no. It’s up to them.”

Saturday, construction crews could be seen working on the site, presumably to try to finish the job by Nov. 22. Every day after that date, Birnam faces a monetary penalty.

But Thompson is hopeful the crews will be able to finish the job on time finishing the underground services this week and paving and laying sidewalk next week. “Starbright (Christmas productions) start on the 24th so we’d like to have the road open by then,” he says. “It is important for the business for the road to be open and for the people of the town for the road to be open.”

Share This

Image
Front Page

Firefighters, specialized equipment from St. Clair, local industry help put out ethanol plant fire in Chatham

September 16, 2026

The Independent Firefighters from Lambton County were among the first responders called to an early morning blaze at Chatham’s Ethanol Plant. Chatham-Kent firefighters were called to the Greenfield Global facility around midnight for a fire. By 3 am, firefighters from St. Clair Township, Borouge International – formerly NOVA – and Shell were on the scene to help with about 15

Read More

Image
Front Page

Enniskillen wants International Plowing Match info

September 16, 2026

Blake Ellis/The Independent The Township of Enniskillen will reach out to the Ontario Plowmen’s Association (OPA) to meet about plans for the International Plowing Match to be hosted in the township in 2027. During the Sept. 8 council meeting, Councillor Tim Williams questioned whether the township had been notified about the 2027 International Plowing Match. It was announced in April

Read More

Image
Front Page

Basement leak latest problem during Moore Sportsplex reno

September 16, 2026

The Independent Groundwater is seeping into the basement of the Mooretown Sports Complex It’s another problem uncovered during the renovation of the pool. Before the pool work began in April, council agreed to rebuild the change room. Contractors had found iron pipes in the walls were corroding. After finding some cash in the budget, council okayed that work. Then, in

Read More

Image
Front Page

Flags honour Nisbet, secure first win in home opener

September 16, 2026

Barry Wright/The Independent Casey Schouten scored four times, including a natural hat trick in the second period, to lead the Mooretown Flags toa 6-1 win over Walpole Island in the PJHL opener at the Moore Sports Complex last Saturday night. Jace Dupuis had a goal and three assists for the Flags while Wes Robertson had the other goal for Mooretown.

Read More