Image

Highland Glen boat ramp fix tops $3 million

June 2, 2021

Heather Wright/The Independent

An engineer’s report says the Highland Glen Conservation Area boat ramp and shoreline needs $3.34 million in repairs over the next 10 years.

In 1990, a steel sheet pile wall with an armour stone breakwater was installed on the northeast side of the ramp which is heavily used by local boaters.
A steel sheet pile breakwater was connected to the existing groyne on the southwest side.

But in late 2019, the original groyne wall on the west side of the boat launch ramp was damaged due to wave action and is now missing. Water levels on Lake Huron have been high, contributing to erosion on both the east and west sides of the ramp protection structure. The erosion has exposed the steel sheet pile wall of the boat ramp and has eroded the banks further along the beach.

The banks have continued to erode, putting the parking lot in jeopardy.
The conservation authority closed the boat ramp in 2019, and received dozens of complaints.

Aecom Engineering has been trying to come up with a fix for some time. Greg Wilcox, the manager of conservation areas, says while much of the study has been complete, the company is still looking at parts of the boat ramp which could not be reached in last fall’s poor weather.

Aecom, in the report to the St. Clair Region Conservation Authority, says the boat ramp could be temporarily fixed for about $85,500.

That would include repairing the walkways on the dock, providing aluminum stairways for beach access and putting up rip rap – a temporary fix until the steel retaining wall is replaced. It would also require a floating breakwater structure to reduce the wave action inside the marina.

But the report also lays out what will be needed in the long term with $709,000 in repairs needed in the next three years, another $710,000 in the next five years and the $550,000 replacement of the ramp.

The engineering firm also suggests replacing the erosion control at a cost of $1.29 million.

Wilcox says the cost of bringing the boat launch up to standards is quite high – much higher than some of the shoreline control projects done regularly along the lake.

The only way the conservation authority generates cash at the site is through a $15 launch fee. Wilcox says that won’t even come close to covering the costs.

He expects that would mean the project – if it is approved by the conservation authority – would need some major government grants to go ahead.

Wilcox says the board likely won’t consider the full engineering report until September, well after the boating season is over.

He knows that won’t go over well with boaters who like to use the launch.

Wilcox says when it first closed, the conservation authority received calls from about 60 people asking what was going on. Now, he receives several calls a week asking when the launch will be open.

Wilcox acknowledges the costs of the repairs will be high, but says the authority also has to consider safety. Highland Glen is the only public boat launch between Grand Bend and Sarnia and boaters need the port in a storm.

Share This

Image
Front Page

The Independent among top newspapers in Canada

September 18, 2024

The Independent The Independent of Petrolia and Central Lambton has won four national awards at the Canadian Community Newspaper Awards. Newspapers of similar circulation size compete against each other and are judged by a panel of industry experts in 27 categories. There were nearly 800 entries this year. The Independent placed second in its division in the prestigious Best All-Around

Read More

Image
Front Page

‘Opportunity to make some money’ now says wind developer

September 18, 2024

Wind project generate $500,000 a year for Brooke-Alvinston Heather Wright/The Independent Peter Budd says the crunch is on for new power sources and municipal governments have a chance to make some cash. The representative of Venfor Inc – a team of developers and entrepreneurs with decades of experience in the Ontario electricity and natural gas sectors according to a filing

Read More

Image
Front Page

Petrolia for cash in second round of housing funding

September 16, 2024

Heather Wright/The Independent Petrolia is hoping the second time will be a charm. The town will again apply for the federal government’s Housing Accelerator Fund. The federal program was announced early in 2024 and early this summer Petrolia and Plympton-Wyoming and Warwick were shut out of funding which would have allowed the municipalities to attract more affordable housing investment in

Read More

Image
Front Page

Town may recognize Petrolia White Rose Band with plaque

September 16, 2024

Heather Wright/The Independent Norm Sutherland wants Petrolia to honour its musical history. He’s written a letter to town council asking if it will consider erecting a plaque at the new bandshell, built as a legacy project during the town’s 150th anniversary. “Mr. Percie Cox, musical director of the Petrolia White Rose Band and teacher of almost all of the youngsters

Read More