Image

Pipeline under St. Clair almost done

May 11, 2020

Alex Kurial
Local Journalism Initiative

Enbridge’s is on the final phase of the underwater pipeline connection to the United States. 
The gas company had been welding a pipeline that would run deeper underwater than the existing one as part of the repairs to Line 5.
Shell Canada’s property along the LaSalle Line has been the site of the work to piece together numerous 40 foot segments of pipeline, which started in October. All told it added up to a 685 metre segment that has now successfully been pulled from the Canadian side to Michigan across the St. Clair River. The project is estimated to cost around $20 million.
Enbridge senior advisor of community relations Ken Hall says the process was an impressive engineering feat.
“The first milestone was digging the new bore hole underneath the river. We used a horizontal directional drill to blow a hole underneath the river from the American side to the Canadian side. And then we pulled the pipe back through that hole on Wednesday,” Hall says. Following the welding, the pipeline also had to undergo a pressurized water test before being placed.
“River crossings can be challenging, and that’s why it’s a milestone because we did it with no incidents, issues or problems. The pipeline can get stuck when you’re pulling it through the hole, so you’re always concerned about that. But we had no problems at all, so we’re all very happy.”
Next up for Enbridge is connecting this segment of pipe to their facility on Plank Rd. “What we’ll do is tie in valves on each side of the river, and connect it to the pipe that goes into Michigan and the pipe that comes from the river up to our terminal,” Hall says.
He expects this final phase of the pipeline connection project to be completed around the end of June. 
The existing underwater pipe remains in place for the time being. Serving as the oil supplier for refineries in the area, Enbridge will need to schedule a temporary outage (lasting around 72 hours) to complete the connection.  
Hall says COVID safety regulations brought extra challenges, but the project went off safely with nobody getting sick. “We did all the work with social distancing, which is challenging when you’re building something. We’re really happy with the safety that’s been applied to this project, in what are obviously very abnormal conditions for everyone. Being able to do the work with that extra challenge, we’re really proud of the accomplishments so far.”

Share This

Image
Front Page

Bright’s Grove library construction expected to start in July

June 22, 2026

Heather Wright/The Independent Construction on the $5.8 million upgrade at the Bright’s Grove Library will start a little in sooner than expected. And that means the Gallery in the Grove will close Saturday. Since 2017, Lambton County, which provides staff and operates the library, and the City of Sarnia, which owns the building, have been talking about expanding the library.

Read More

Image
Front Page

One scrappy Hometown Hero

June 22, 2026

Blake Ellis/The Independent The young man they call the P-Town Scrapper was among four people honoured by the Toastmasters of Petrolia as Hometown Heros. Cathy Tong presented the awards to four people whose dedication to the community and volunteerism may not otherwise be recognized. She organized the contest saying she wanted to honour people in Petrolia and area who do

Read More

Image
Front Page

Community to raise $5M for Grand Bend centre

June 22, 2026

The Independent Lambton Shores council has given the okay to draw up building plans for the proposed Grand Bend Community Centre project. The $15 million centre project was given the green light by council in May with a request for staff to come up with a way to fundraise for some of the cost. Staff suggested, and council agreed, to

Read More

Image
Front Page

Housing in Thedford warehouse needs MOE’s approval

June 19, 2026

The Independent A developer’ plans to build apartments in Thedford will have to wait. Robert Hewitt owns a former Grand Trunk Railway warehouse on Pearl Street and wants to create apartments upstairs. Lambton Shores council isn’t opposed, but says benzene has been found on the property. The amount is small and doesn’t affect the commercial use of the property, but,

Read More