Image

Pipeline under St. Clair almost done

May 11, 2020

Alex Kurial
Local Journalism Initiative

Enbridge’s is on the final phase of the underwater pipeline connection to the United States. 
The gas company had been welding a pipeline that would run deeper underwater than the existing one as part of the repairs to Line 5.
Shell Canada’s property along the LaSalle Line has been the site of the work to piece together numerous 40 foot segments of pipeline, which started in October. All told it added up to a 685 metre segment that has now successfully been pulled from the Canadian side to Michigan across the St. Clair River. The project is estimated to cost around $20 million.
Enbridge senior advisor of community relations Ken Hall says the process was an impressive engineering feat.
“The first milestone was digging the new bore hole underneath the river. We used a horizontal directional drill to blow a hole underneath the river from the American side to the Canadian side. And then we pulled the pipe back through that hole on Wednesday,” Hall says. Following the welding, the pipeline also had to undergo a pressurized water test before being placed.
“River crossings can be challenging, and that’s why it’s a milestone because we did it with no incidents, issues or problems. The pipeline can get stuck when you’re pulling it through the hole, so you’re always concerned about that. But we had no problems at all, so we’re all very happy.”
Next up for Enbridge is connecting this segment of pipe to their facility on Plank Rd. “What we’ll do is tie in valves on each side of the river, and connect it to the pipe that goes into Michigan and the pipe that comes from the river up to our terminal,” Hall says.
He expects this final phase of the pipeline connection project to be completed around the end of June. 
The existing underwater pipe remains in place for the time being. Serving as the oil supplier for refineries in the area, Enbridge will need to schedule a temporary outage (lasting around 72 hours) to complete the connection.  
Hall says COVID safety regulations brought extra challenges, but the project went off safely with nobody getting sick. “We did all the work with social distancing, which is challenging when you’re building something. We’re really happy with the safety that’s been applied to this project, in what are obviously very abnormal conditions for everyone. Being able to do the work with that extra challenge, we’re really proud of the accomplishments so far.”

Share This

Image
Front Page

First part of Petrolia water pipeline installed

October 1, 2026

Heather Wright/The Independent

Read More

Image
Front Page

Lancers baseball team aims for regional title

October 1, 2026

Ryan Aarts/The Independent After a strong season last year, the LCCVI Lancers baseball team is looking to build on its success and make another run at a LKSSAA championship. The Lancers had just one loss last season, finishing 7-1 with that loss coming at an unfortunate time to Ursuline College in the LKSSAA final. Despite falling short, the experience has

Read More

Image
Front Page

Henderson to be new leader of Lambton IPM

September 30, 2026

The Independent The Lambton County International Plowing Match has a new leader. Dave Henderson will lead the group bringing the massive farm show to Lambton County in 2027. The 2027 IPM was originally planned at the Brigden Fairgrounds. Planning was well underway when the local committee quit saying it would not host the event because a deal was not in

Read More

Image
Front Page

Petrolia can’t afford bigger arena alone: candidates

September 30, 2026

Heather Wright/The Independent If there is a new arena to be build in Petrolia, it only happen with help from the town’s neighbours. That’s the opinion of the people who are vying for councillor positions around the town council table Oct. 26 about a request for a double ice pad which came to council more than two years ago. Lisa

Read More