Image

Pipeline under St. Clair almost done

May 11, 2020

Alex Kurial
Local Journalism Initiative

Enbridge’s is on the final phase of the underwater pipeline connection to the United States. 
The gas company had been welding a pipeline that would run deeper underwater than the existing one as part of the repairs to Line 5.
Shell Canada’s property along the LaSalle Line has been the site of the work to piece together numerous 40 foot segments of pipeline, which started in October. All told it added up to a 685 metre segment that has now successfully been pulled from the Canadian side to Michigan across the St. Clair River. The project is estimated to cost around $20 million.
Enbridge senior advisor of community relations Ken Hall says the process was an impressive engineering feat.
“The first milestone was digging the new bore hole underneath the river. We used a horizontal directional drill to blow a hole underneath the river from the American side to the Canadian side. And then we pulled the pipe back through that hole on Wednesday,” Hall says. Following the welding, the pipeline also had to undergo a pressurized water test before being placed.
“River crossings can be challenging, and that’s why it’s a milestone because we did it with no incidents, issues or problems. The pipeline can get stuck when you’re pulling it through the hole, so you’re always concerned about that. But we had no problems at all, so we’re all very happy.”
Next up for Enbridge is connecting this segment of pipe to their facility on Plank Rd. “What we’ll do is tie in valves on each side of the river, and connect it to the pipe that goes into Michigan and the pipe that comes from the river up to our terminal,” Hall says.
He expects this final phase of the pipeline connection project to be completed around the end of June. 
The existing underwater pipe remains in place for the time being. Serving as the oil supplier for refineries in the area, Enbridge will need to schedule a temporary outage (lasting around 72 hours) to complete the connection.  
Hall says COVID safety regulations brought extra challenges, but the project went off safely with nobody getting sick. “We did all the work with social distancing, which is challenging when you’re building something. We’re really happy with the safety that’s been applied to this project, in what are obviously very abnormal conditions for everyone. Being able to do the work with that extra challenge, we’re really proud of the accomplishments so far.”

Share This

Image
Front Page

Remembering Newell Hastings

June 14, 2025

Heather Wright/The Independent Sunday, Newell Hasting’s service to King and Country over a century ago was remembered in a peaceful church cemetery near Watford. Hasting was born in Petrolia and his family moved to Watford around the turn of the century. He signed up to serve in the miltia with Watford’s 149th Battalion before being called up for service. He

Read More

Image
Front Page

Sidewalk projects around First Ave this summer

June 13, 2025

Heather Wright/The Independent Sidewalks along First Street in Petrolia will be getting an upgrade once school is out for the summer. It’s part of the latest large project to improve the town’s sidewalk system. In 2023, BM Ross and Associates completed a study on Petrolia’s sidewalk system and found it lacking. It suggested $1.5 million in sidewalk construction was needed

Read More

Image
Front Page

Aamjiwnaang evacuates parts of community as INEOS decommissioning increases benzene levels

June 13, 2025

Leaders of the Aamjiwnaang First Nation are evacuating residents between Churchill Road and Tashmoo Ave after high levels of benzene have been detected in the area. Just before noon Friday, INEOS Styrolutions issued a notice saying hourly benzene emissions have been detected about 0.021 parts per million. The company is decommissioning the plant which is within eyesight of Aamjiwnaang’s band

Read More

Image
Front Page

St Philip’s student wins big at national fair

June 13, 2025

The Independent Ben Harper made a splash at the Canada-Wide Science Fair in Fredericton taking home a bronze medal. The Grade 8 student from St. Philip’s in Petrolia presented his climate-focused project called A Wavy Problem – Navigating the Surges of Climate Change last week and won a bronze medal in his division. The Petrolia student tested six different offshore

Read More