Image

November 5, 2015

Clean Harbors has started construction on its multi-million dollar expansion and it’s bringing in some huge equipment to get the job done.

The Ministry of the Environment approved the company’s plan to begin piling waste higher in the existing landfill recently – extending the life of the site by 25 years and piling waste as high as the current 25-foot berms.

Final approval from the ministry came Oct. 12 and Mike Parker,  Clean Harbors vice president of environmental compliance, says work began almost immediately.

There are two major parts to the expansion. The company is creating a waste receiving area and digging a new collection pond and deep trenches to collect any run off.

Parker says the company is building a large concrete pad which leads to a preformed steel basin. Parker says the trucks coming in will drive up to the pad and drop their waste into the steel basin. Clean Harbors staff will then take the waste to be treated.

Right now, trucks drive in and dump the waste themselves but as the site fills, trucks would have to drive on top of waste to drop off their loads. The concrete pad will eliminate that.

“That way any vehicles coming in from off site don’t come into contact with the waste,” says Parker. “Driving into a hazardous landfill site doesn’t work out…the trucks end up driving some of the waste off site and that just doesn’t work for us.”

A new process water pond is also being dug now. “The majority of the soil is being used to make a platform to bring a special trenching machine in from the States,” says Parker.

The machine will, in one pass, dig a trench between five and seven feet deep, lay gravel and the piping. “The trench is to collect the leachate …and every 200 or 300 meters a sump is drilled down nine meters, that’s where it is all collected…Any leachate moves into the trench and anything slightly outside of it is sucked in,” says Parker. “Everything goes down through the trench, is pumped to the leachate pons or tanks and then sent to the incinerator for treatment.”

The trenching is expected to be done in a couple of weeks. The contractor has to have a special heavy haul permit to bring the equipment and a special track used to operate it overland. It’s expected to arrive at the end of this week.

The company hopes construction can be complete by the end of November. It’s expected to cost between $5 and $7 million.

Share This

Image
Front Page

Firefighters, specialized equipment from St. Clair, local industry help put out ethanol plant fire in Chatham

September 16, 2026

The Independent Firefighters from Lambton County were among the first responders called to an early morning blaze at Chatham’s Ethanol Plant. Chatham-Kent firefighters were called to the Greenfield Global facility around midnight for a fire. By 3 am, firefighters from St. Clair Township, Borouge International – formerly NOVA – and Shell were on the scene to help with about 15

Read More

Image
Front Page

Enniskillen wants International Plowing Match info

September 16, 2026

Blake Ellis/The Independent The Township of Enniskillen will reach out to the Ontario Plowmen’s Association (OPA) to meet about plans for the International Plowing Match to be hosted in the township in 2027. During the Sept. 8 council meeting, Councillor Tim Williams questioned whether the township had been notified about the 2027 International Plowing Match. It was announced in April

Read More

Image
Front Page

Basement leak latest problem during Moore Sportsplex reno

September 16, 2026

The Independent Groundwater is seeping into the basement of the Mooretown Sports Complex It’s another problem uncovered during the renovation of the pool. Before the pool work began in April, council agreed to rebuild the change room. Contractors had found iron pipes in the walls were corroding. After finding some cash in the budget, council okayed that work. Then, in

Read More

Image
Front Page

Flags honour Nisbet, secure first win in home opener

September 16, 2026

Barry Wright/The Independent Casey Schouten scored four times, including a natural hat trick in the second period, to lead the Mooretown Flags toa 6-1 win over Walpole Island in the PJHL opener at the Moore Sports Complex last Saturday night. Jace Dupuis had a goal and three assists for the Flags while Wes Robertson had the other goal for Mooretown.

Read More