Image

November 5, 2015

Clean Harbors has started construction on its multi-million dollar expansion and it’s bringing in some huge equipment to get the job done.

The Ministry of the Environment approved the company’s plan to begin piling waste higher in the existing landfill recently – extending the life of the site by 25 years and piling waste as high as the current 25-foot berms.

Final approval from the ministry came Oct. 12 and Mike Parker,  Clean Harbors vice president of environmental compliance, says work began almost immediately.

There are two major parts to the expansion. The company is creating a waste receiving area and digging a new collection pond and deep trenches to collect any run off.

Parker says the company is building a large concrete pad which leads to a preformed steel basin. Parker says the trucks coming in will drive up to the pad and drop their waste into the steel basin. Clean Harbors staff will then take the waste to be treated.

Right now, trucks drive in and dump the waste themselves but as the site fills, trucks would have to drive on top of waste to drop off their loads. The concrete pad will eliminate that.

“That way any vehicles coming in from off site don’t come into contact with the waste,” says Parker. “Driving into a hazardous landfill site doesn’t work out…the trucks end up driving some of the waste off site and that just doesn’t work for us.”

A new process water pond is also being dug now. “The majority of the soil is being used to make a platform to bring a special trenching machine in from the States,” says Parker.

The machine will, in one pass, dig a trench between five and seven feet deep, lay gravel and the piping. “The trench is to collect the leachate …and every 200 or 300 meters a sump is drilled down nine meters, that’s where it is all collected…Any leachate moves into the trench and anything slightly outside of it is sucked in,” says Parker. “Everything goes down through the trench, is pumped to the leachate pons or tanks and then sent to the incinerator for treatment.”

The trenching is expected to be done in a couple of weeks. The contractor has to have a special heavy haul permit to bring the equipment and a special track used to operate it overland. It’s expected to arrive at the end of this week.

The company hopes construction can be complete by the end of November. It’s expected to cost between $5 and $7 million.

Share This

Image
Front Page

ICYMI: Record-breaking crowd at Alvinston Rodeo

June 20, 2025

Heather Wright/The Independent Like the movie says; if you build it, they will come. The Alvinston Pro Rodeo committee brought in larger stands hoping to accommodate visitors to the three-day event. Saturday night, those stands were filled and there were still people looking for seats according to Chairman Dan Cumming. Here’s just some of the action from the event:

Read More

Image
Front Page

Lambton Public Health issues first heat warning of the summer

June 20, 2025

FROM LAMBTON PUBLIC HEALTH With the prediction of hot and humid weather expected to start on Saturday,June 21 and continue into next week, Environment and Climate Change Canada is issuing a HeatWarning for Lambton County. Heat warnings are issued when two or more consecutive days of daytime maximum temperatures areexpected to reach 31°C or warmer and nighttime minimum temperatures are

Read More

Image
Front Page

Rural bus service starts making stops in Wyoming Monday

June 20, 2025

Heather Wright/The Independent Before there was money to bring a bus into Wyoming, Susan Mills was answering questions from residents about a new rural transit system. The Town of Plympton-Wyoming became a partner in the rural transit system called Huron Shores Area Transit earlier this spring. But service didn’t begin immediately. Lambton Shores, which runs the system, and its partners,

Read More

Image
Front Page

Why spend $20K to study a bridge to nowhere: McEwen

June 20, 2025

Heather Wright/The Independent Plympton-Wyoming Deputy Mayor Netty McEwen says it doesn’t make sense to spend $20,000 to study a bridge that goes nowhere. Paul daSilva, Director of Public Works, in a report to council June 11, suggested spending $40,000 to do Municipal Environmental Assessments on two low-traffic bridges, one on O’Brien Road, the other on Elmsley Road. “I took a

Read More