Image

First part of Petrolia Line construction will take a few more weeks

July 27, 2016

Heather Wright

The Independent

It will be mid to late August before the construction between Fletcher and King Street is complete.

Construction on the second phase of the $5.3 million project got underway in June with hope that the first stretch of roadway could be done as early as late July.

Petrolia’s Director of Operations, Mike Thompson says that may have been overly optimistic. “That was originally the preliminary estimate… but the unofficial time is now mid to late August,” he tells The Independent.

“There weren’t necessarily delays; I don’t think they’re behind. I think in part it was wishful thinking. The reality is it’s going to be mid to late August.”

Over the next few weeks, Henry Heyink Construction workers will be stripping down the excess dirt on the road and rebuilding it with granular material before beginning to pave the first phase.

In the meantime, additional workers have been brought in to prepare for the second phase which will repair all the way to Kerby Street. Early this week, crews were setting up  fencing and a temporary water line on the main street. The water work caused problems on Robert Street, leading to the street being closed down for a few hours Tuesday while town work crews repaired them.

Thompson says while the paving of the first phase will take longer than expected, he’s confident the end result will still be good.

“All we really care about is the end date,” he says noting the contract stipulates the contractor have the street reopened by the end of October.

“This year, they’re pretty confident, they are going to hit that date and they have tonnes of people working on it.

“The most important date is the last one.”

Share This

Image
Front Page

Firefighters, specialized equipment from St. Clair, local industry help put out ethanol plant fire in Chatham

September 16, 2026

The Independent Firefighters from Lambton County were among the first responders called to an early morning blaze at Chatham’s Ethanol Plant. Chatham-Kent firefighters were called to the Greenfield Global facility around midnight for a fire. By 3 am, firefighters from St. Clair Township, Borouge International – formerly NOVA – and Shell were on the scene to help with about 15

Read More

Image
Front Page

Enniskillen wants International Plowing Match info

September 16, 2026

Blake Ellis/The Independent The Township of Enniskillen will reach out to the Ontario Plowmen’s Association (OPA) to meet about plans for the International Plowing Match to be hosted in the township in 2027. During the Sept. 8 council meeting, Councillor Tim Williams questioned whether the township had been notified about the 2027 International Plowing Match. It was announced in April

Read More

Image
Front Page

Basement leak latest problem during Moore Sportsplex reno

September 16, 2026

The Independent Groundwater is seeping into the basement of the Mooretown Sports Complex It’s another problem uncovered during the renovation of the pool. Before the pool work began in April, council agreed to rebuild the change room. Contractors had found iron pipes in the walls were corroding. After finding some cash in the budget, council okayed that work. Then, in

Read More

Image
Front Page

Flags honour Nisbet, secure first win in home opener

September 16, 2026

Barry Wright/The Independent Casey Schouten scored four times, including a natural hat trick in the second period, to lead the Mooretown Flags toa 6-1 win over Walpole Island in the PJHL opener at the Moore Sports Complex last Saturday night. Jace Dupuis had a goal and three assists for the Flags while Wes Robertson had the other goal for Mooretown.

Read More